JO-4506 — 9358-HTB
01:05 PM7
All job ordersTo Plant
9358-HTB
Saudi Readymix RM08 • Jada Projects • Al Malqa Development
C32/40 Pump • 10 m³ load • Order ORD-4486
Total Time
2h 16m 29s
Pouring Time
47m 23s
Waiting Pouring Time
19m 53s
Speed
32 km/h
Unexpected Stops
6
Stage log
| Stage | Time | Leg duration | State |
|---|---|---|---|
| Loading | 10:49 AM | — | Completed |
| To Job | 11:06 AM | 16m 37s | Completed |
| On Job | 11:38 AM | 32m 30s | Completed |
| Pouring | 11:46 AM | 8m 02s | Completed |
| To Plant | 12:34 PM | 31m 57s | In progress |
| At Plant | ~ 01:20 PM | 46m 16s | Pending |